2015.12.20


 

The end of the 72 hour Site Acceptance Test of Ecotube System DeNOx installation installed on the stoker boiler No K5, type EKM50-Md at Megatem Heat & Power Plant in Lublin, Poland.

We are pleased to announce that on 20th December 2015 the 72 hours test run and Site Acceptance Test of Ecotube System DeNOx installation was completed with a positive result. Ecotube System have been installed by ICS on the stoker boiler type EKM50-Md number K5 at Megatem Heat & Power Plant in Lublin, Poland to reduce emissions of nitrogen oxides (NOx). Trial operation confirmed the smooth and trouble-free operation of the equipment and installation of Ecotube System. In total ICS has supplied and commissioned three independent Ecotube Systems flue gas DeNOx system in Megatem and Heat & Power Lublin (Poland) Achieving reduction of NOx to value below 180 mg/Nm3.